Clark County Washington
Home Find It! A-Z Index Departments & Programs Jobs Contact Us
     
Public Works >Klineline Bridge Replacement > Construction photographs

CONTACT US

Linda Small
Project Manager
(360) 397-6118 ext. 4753
Linda.Small@clark.wa.gov

Jim Gladson
Public Information
(360) 397-6118 ext. 4398
Jim.Gladson@clark.wa.gov

Clark County Public Works
PO Box 9810
Vancouver WA 98666-
9810

Comment form

Construction photographs

The new bridge is now complete. The link to a larger version under each photo takes you to a higher resolution JPEG file. Thank you for visiting this site.

The Bridge Is Open -- September 26 Dedication
parade Bridge Planted medians
Local business owners and neighborhood leaders paraded across the bridge
Larger photo
All sides of the new bridge are fully landscaped and the restored Salmon Creek flows freely.
Larger photo

The bridge is ready again to carry more than 17,000 car a day.
Larger photo

     
Speech Restored Pool
Commissioner Betty Sue Morris welcomed dozens of people to the dedication event.
Larger photo
This view from the bridge looking downstream shows the new channel created in Salmon Creek.
Larger photo
Local resident Brad Lothspeich spoke at the dedication representing businesses and neighborhoods.
Larger photo
     

.

New bridge nearly complete -- September 12 Photos
artist view Bridge Planted medians
Artist rendering shows finished bridge with arches on the sides. Photos to right show this phase under construction.
Larger photo
The temporary bridge is gone, and the new bridge is near completion.
Larger photo

Medians have been landscaped and paving is underway.
Larger photo

     
Road paving Restored Pool
Roadway south of the bridge received final paving September 12. North side paving begins September 15.
Larger photo
This view from the bridge looking downstream shows the new channel created in Salmon Creek.
Larger photo
The pools and riffles created in Salmon Creek will provide much better fish passage upstream.
Larger photo
     

 

Making a new bridge -- September 3 Photos
artist view Sidewalks Equipment digging
Artist rendering shows finished bridge with arches on the sides. Photos to right show this phase under construction.
Larger photo
Bridge sidewalks have been poured. Pipes at lower right are for conduit for electrical lines.
Larger photo

The temporary bridge and sewer bypass pipe are being removed. Instream work will follow
in that area.
Larger photo

     
Temporary dam Excavating Installing
This dam has been holding back and diverting Salmon Creek since spring. Later in September the creek will be released to flow freely beneath the new bridge.
Larger photo
Final utility pipe installation must be completed before final road paving can begin.
Larger photo
Median and street side planters are now receiving topsoil. Acutual planting will be done later in the fall.
Larger photo
     
Making a new bridge -- August 19 Photos
artist view arches building overlook
Artist rendering shows finished bridge with arches on the sides. Photos to right show this phase under construction.
Larger photo
Workers put finishing touches on the arch walls. These will be painted later.
Larger photo
Each side of the bridge includes a wide overlook for viewing Salmon Creek. Work is starting on those now.
Larger photo
     
Temporary dam Road Sidewalk
This dam has been holding back and diverting Salmon Creek since spring. Later in September the creek will be released to flow freely beneath the new bridge.
Larger photo
Bridges go up in stages. The deck has been poured. Now framing is underway for approaches that will connect with Highway 99
Larger photo
Businesses south of the bridge will have new curbs and sidewalks with planters.
Larger photo
     

 

Making a new bridge -- July-August Latest Photos
artist view arches 1 forms on bridge
Artist rendering shows finished bridge with arches on the sides. Photos to right show this phase under construction.
Larger photo
Forms are being built to create side arches for the new bridge.
Larger photo
The next arch section is almost ready to be installed. Once in place, the contractor will pour concrete to create the finished arches.
Larger photo
     
asphalt lift surveyors utlities
The contractor has already poured the first of three layers or "lifts" of asphalt on Highway 99 south of the bridge
Larger photo
County surveyors check bridge and road alignments and elevations frequently during construction.
Larger photo
The new bridge will carry six different utility connections when complete.
Larger photo
     

 

Making a new bridge -- July 16 Latest Photos
Bridge deck long shot Men talking on bridge road construction
The bridge deck is now poured and covered in white plastic to cure the concrete.
Larger photo
County Construction Manager stands on the new bridge deck with the bridge contractor.
Larger photo
The new road south of the bridge takes shape.
Larger photo
     
median planter stormwater pond two bridges
This median south of the bridge will be planted this fall with trees and shrubs. Paving starts in late July.
Larger photo
A large new pond downstream of the bridge will handle stormwater runoff and protect Salmon Creek.
Larger photo
The temporary bridge and sewer bypass (right) will be removed in August and a new line will be hung below the bridge
Larger photo
     

aking

Making a new bridge -- June 20 Latest Photos
Sewer manhole girders installed Creek restoration
The bridge replacement also includes major storm and sanitary sewer installation
Larger photo
All girders are in place. Deck installation should begin soon.
Larger photo
In-water work to reshape Salmon Creek into a fish friendly stream is well advanced.
Larger photo
     
Warning sign Pouring pilasters Pouring concrete for new bridge foots
People have been crossing the bridge. This is dangerous. Keep off!
Larger photo
One of four corner posts that will hold lights for the finished bridge.
Larger photo
Highway 99 south of the bridge will be raised about 3 feet on the west side to flatten the curve.
Larger photo
     

 

Making a new bridge -- June 9-10 Girder Installation
First girders installed Girder in the air Trucks carried girders
The first four girders went in Monday, June 9.
Larger photo
Two cranes lift each girder into place from opposite sides of the bridge
Larger photo
Each girder is 153 feet long. These trucks traveled down I-5 from Tacoma.
Larger photo
     
Girder almost placed Measuring the girder Pouring concrete for new bridge foots
Two cranes gently place girder #5 June 11. Each girder weighs 86 tons.
Larger photo
Each girder must be carefully measured to make certain it is straight and level.
Larger photo
Rebar at the top of each girder will help stablize the new bridge deck.
Larger photo
     

 

Demolition of the Klineline Bridge ~ May 28, 2008
Old bridge is gone Data and phone cables still cross the creek Sheet pile is soon removed
The old bridge is gone
Larger photo of demolition
Phone and data cables still cross the creek on separate supports
Larger photo of demolition
Sheet pile that once protected old bridge piers will soon be removed.
Larger photo of sheet pile
     
Major improvment for fish included in project Improved channel will help fish migration Pouring concrete for new bridge foots
The project will include major improvements for fish in Salmon Creek.
Larger photo of creek
It looks bad now, but when complete this improved stream channel will help fish migrate upstream.
Larger photo of creek
The contactor is currently pouring concrete for new bridge foots on the north and south banks of Salmon Creek.
Larger photo of concrete pour
     

 

Demolition of the Klineline Bridge ~ May 2008
Preparation of bridge Preparation of bridge Closeup of demolition
Creek diverted around bridge construction site.
Larger photo of diversion
Machinery drills shafts for new bridge supports
Larger photo of preparation
Powerful jaws crush concrete during bridge demolition May 16
Larger photo of closeup
     
Demolition May 16 Demolition May 17 Demolition May 17
Salmon Creek will be fully restored as part of the new bridge project
Larger photo of demolition
By May 17 most of the old bridge deck was gone.
Larger photo of demolition
Demolition May 17
Larger photo of demolition
     

 

April, 2008
View across bridge View from downstream View from upstream
Work began in mid April with utility removal from the old bridge.
Larger photo across
Major phone and data lines have been removed from the bridge.
Larger photo downstream
Contractor built a temporary bridge to support a sewer line bypass.
Larger photo upstream
     
Pipes photo Rebar and pipes Excavator photo
These pipes will be used for stream diversion.
Larger photo of pipes
The contractor began staging equipment and materials in mid April.
Larger photo of rebar
Excavator
Larger photo of excavator
     

Clark County Public Works - Engineering: Heath Henderson, Manager
Street Address: 1300 Franklin Street, 4th Floor, Vancouver, WA 98660
Mailing Address: P.O. Box 9810, Vancouver, WA 98666-9810
Main phone: (360) 397-6118 ext. 4944 | FAX: (360) 397-6051
TTY: (360) 397-6057
E-mail: pubwks.cservice@clark.wa.gov

Clark County Home | Find It! | A-Z Index | News Releases | Jobs | Contact Us

For questions or comments regarding the Clark County Web site: Webmaster@clark.wa.gov

© 2008 Clark County Washington | Disclaimer and legal notice | Health Information Privacy Notice