Priorities and approximate timelines
- Update use agreements with Federal Bureau of Investigation; Clark County Sheriff’s Office; Bureau of Alcohol, Tobacco, Firearms, and Explosives; and Metro Explosives Disposal Unit
- Quarter 3, 2025
- Improve access control security at the Camp Bonneville main gate
- Quarter 1, 2025
- Update, June 2025: Clark County Public Works now maintains control of access at the entrance gate
- Update, September 2025: The FBI access panel has been disabled. Public Works will develop a standard procedure for granting access permissions to county staff and contractors.
- Support Washington Department of Ecology in finalizing the draft periodic review for presentation to the community
- Quarter 4, 2025
- Complete a fence repair and upgrade project near Livingston Mountain quarry
- Quarter 3, 2025
- Update, September 2025: The fence repair project has been completed. The previous section of fence in this location was a five-strand barbed wire fence. The fence was repaired to address issues with trespassing onto the property. Click here for a photograph of the complete project.
- Maintain and repair fence
- Ongoing
- Open bid for road maintenance pilot project, for construction services for maintenance of several miles of general access roads at Camp Bonneville
- Quarter 3, 2025 (notice to contractors)
- Update, September 2025: Contractor Swofford Excavating will be blading and regrading multiple existing forest road locations along the south side of the property. Work will also include culvert replacements. Work is expected to begin in September and be completed by quarter 4.
- Demolish four barrack structures within the Camp Killpack cantonment. These structures were selected for demolition because of their poor condition.
- Quarter 4, 2025
- Update, September 2025: Contractor Groat Brothers will be removing four temporary barracks structures. This includes the demolition of the four structures, removal and disposal of debris, backfilling and restoration of the project area. Debris will be disposed of off-site with care taken to manage paint identified as being lead-based. Work will begin in mid-September and is expected to be completed within a few weeks.
- Plan shaded fuel break: mapping and layout of shaded fuel break units prioritizing portions of west, north, and south boundaries for brush removal and timber sale
- Quarter 4, 2025
- Update, June 2025: proposals received in May 2025 are currently being evaluated
- Update, September 2025: A contractor has been selected. Work will be completed in Quarter 4, 2025 and Quarter 1, 2026. Public Works is seeking to present this information to council in a work session sometime in Quarter 1, 2026.
- Support Washington Department of Ecology in finalizing the Remedial Investigation/Feasibility Study for Remedial Action Unit 2c or Landfill 4/Sitewide Groundwater
- Quarter 4, 2025 and Quarter 1, 2026
- Repair damaged signage along fence lines
- Quarter 4, 2025
- Install signage along Central Valley Floor roads, informing public about past military use of Camp Bonneville
- Quarter 3, 2025
- Update, September 2025: Completed. Click here to view a photo of the type of sign that has been installed. Additional signs will be installed along roads and trails outside of the Central Valley floor.
- Replace and improve gates restricting access into the Central Impact Target Area (CITA), and install additional gates outside the CITA to provide a 500' buffer to further restrict access to the CITA
- Quarter 4, 2025
- Upgrade site security with installation of onsite cameras in select locations
- Quarter 4, 2025
- Update, September 2025: Installation began in early September.
- Develop site-specific health and safety plan, institutional control manual, and long-term operations and maintenance plan for Camp Bonneville
- Quarter 4, 2025
- Update, September 2025: A draft of a site-specific health and safety plan has been developed, but will continue to be updated. The long-term operations and maintenance plan is currently in development.