Week of July 14, 2025
Clark County 564.397.6118
This webpage shows county projects on county roads that could have an impact on the traveling public. A variety of private development projects may be occurring throughout the county that might not be listed. For more information on proposed development projects, visit clark.wa.gov/community-development/proposed-developments. For more information on the process of approving proposed development projects visit, clark.wa.gov/community-development.
Construction Closures and Delays
Railroad Roadbed Rehabilitation Project
Most of the work for the Railroad Roadbed Rehab was completed last week. The only work remaining is clearing and grubbing along the track South to Battleground.
Summer Road Preservation - Northeast 72nd Avenue
On July 14, Northeast 72nd Avenue, between SR 502 and Northeast 259th Street, will be closed for road preservation work. This is part of the ongoing road surface preservation treatments that occurs every summer.
The roadway will be closed from approximately 7 am to 7 pm. Work is weather-dependent.
This spring, Clark County will upgrade several traffic signals throughout the county.
This work includes constructing or upgrading traffic and pedestrian signals at:
- Northeast 27th Avenue at Northeast 134th Street
- Northeast 7th Avenue at Northeast Fraser Road
- Northeast 5th Avenue at Northeast 78th Street
- Northeast Hazel Dell Avenue – from Northeast 78th Street to Northeast 82nd Street
Construction is expected to begin in mid-April. Construction activities will occur between 7 a.m. and 5 p.m. on weekdays. For the safety of workers and the public, traffic lanes and/or sidewalks may be temporarily closed near worksites. Travels will be directed around closed lanes and sidewalks.
Northeast Sunset Falls Road Pavement Preservation
Construction has been delayed until summer 2025 due to challenges in obtaining materials and the onset of cold and wet weather.
Heritage Farm Wetland Restoration
Construction has begun at Heritage Farm for their wetland restoration. The contractor has begun clearing and grubbing on site and setting up erosion control and construction fencing. This week, they plan on beginning work on the new sanitary sewer line that run adjacent to the wetland.
Construction at Harmony Sports Complex has begun. Last week, the contractor graded the site and added more base course. They also prepared curbs and excavated bio-retention facilities. This week, they plan on installing curb, working on electrical scopes, and irrigation system sleeving.
Construction at Curtin Creek Community Park has begun. The park is anticipated to be open by spring 2026. This week, they plan to continue work on the various storm facilities/infiltration trenches. They also plan to prep for some of the curbing.
Summer preservation is kicking off. Construction to improve the surface of county roads will occur at various locations.
Clark County provides an online interactive map so residents can get a general idea for where the HMA locations are.
2025 Preservation ADA Improvements
Construction for this project has begun. Impacts will include short delays, construction zones, and rerouting of pedestrians.
2024 ADA Ramp Improvement project
Hockinson Meadows Community Park - disc golf trail
The contractor plans to continue work throughout the site and place aggregate for the trail and work on the driveway loop.
Felida Park Senior Housing - NW 39th Ave, Vancouver WA
A new crosswalk and center median on NW 39th Ave. This project will be ongoing with a pave date in August
Northwest 99th Street Water Quality Retrofit (Northwest 11th Avenue to Cougar Creek)
This project will install a large stormwater filter vault to treat runoff from approximately five acres of impervious surfaces along Northwest 99th Street, Northwest 9th Avenue, and surrounding areas. Construction has begun, and travelers can expect traffic delays in the area.
NW 11th Ave between NW 149th St and NW 164th St
A contractor will be doing utility work and paving for a new development between now and mid-September. There will be a single lane closure with flaggers controlling traffic.
A contractor working at NW 99th Street at NW 9th Ave
Fink Construction is working for Clark Public Utilities Water to extend larger water pipes to the west. They are digging a trench along NW 99th Street. At a later time, they will dig into the side streets to make additional connections.
With this activity, the vehicle detectors were dug up before schedule. Our staff is working to provide alternate signal timing that accounts for variable traffic volumes and the high pedestrian traffic at the signal adjacent to the high school.
County engineers will monitor the intersection's performance through the first day of school and make any adjustments needed.
Northshore Waterline - City of Camas
Northeast 28th Street and Northeast 232nd Avenue, Installing Mainline Water Main
Contact: Wisam Jawadi 1-360-335-5712
Interstates, highways
Washington State Department of Transportation
360.905.2060
Private Development Projects Citywide
A variety of private development projects may be occurring throughout the City of Vancouver. For information about these projects, please visit: www.cityofvancouver.us/projects.